# Goal-4 Execution Plan: Memory System v1
|
|
|
|
## Task Sequence
|
|
|
|
1. Goal-4-Task-1: Design memory interface (prerequisite for all other tasks) [COMPLETE]
|
|
2. Goal-4-Task-2: Implement core data structures (depends on Task-1) [COMPLETE]
|
|
3. Goal-4-Task-3: SQLite integration (depends on Task-2) [COMPLETE]
|
|
4. Goal-4-Task-4: Audit logging (depends on Task-1, can proceed in parallel) [COMPLETE]
|
|
|
|
## Dependency Diagram
|
|
|
|
```mermaid
|
|
graph TD
|
|
A[Task-1: Interface Design] --> B[Task-2: Data Structures]
|
|
A --> C[Task-4: Audit Logging]
|
|
B --> D[Task-3: SQLite Integration]
|
|
```
|
|
|
|
## Quality Gates
|
|
|
|
1. Interface design must be reviewed by symphony-score
|
|
2. Data structures must pass security review
|
|
3. SQLite adapter must include encryption tests
|
|
4. Audit logs must meet security baseline requirements
|
|
|
|
## Risk Mitigation
|
|
|
|
- Early interface review to prevent rework
|
|
- Security validation at each stage
|
|
- Modular implementation to isolate dependencies |