# SecureAudit Benchmark Validation Report - Goal 1 Task 5
|
|
|
|
## Test Summary
|
|
- **Task ID**: Goal-1-Task-5
|
|
- **Validation Date**: 2025-05-05
|
|
- **Status**: CONDITIONAL APPROVAL (Pending Security Fixes)
|
|
|
|
## Requirements Verification
|
|
|
|
### Performance Benchmarks (from Goal-3-Task-4)
|
|
| Component | Metric | Target | Actual | Status |
|
|
|-----------|--------|--------|--------|--------|
|
|
| CLI | Response Time | ≤500ms | 487ms | ✅ Pass |
|
|
| CLI | Throughput | N/A | 1250 ops/sec | - |
|
|
| Web | Response Time | ≤500ms | 512ms | ⚠️ Slightly Exceeds |
|
|
| Web | Throughput | N/A | 980 ops/sec | - |
|
|
|
|
### Security Validation (from Goal-1-Task-4)
|
|
| Requirement | Implementation Status | Notes |
|
|
|------------|-----------------------|-------|
|
|
| Encryption | ✅ Fully Implemented | AES-256-GCM, 15ms overhead |
|
|
| RBAC | ✅ Fully Implemented | 42ms overhead, no degradation |
|
|
| Data Obfuscation | ⚠️ Partial | Outstanding medium severity issues |
|
|
|
|
## Outstanding Issues
|
|
1. **Security**:
|
|
- Unencrypted cron expressions (Medium)
|
|
- Plaintext task IDs (Medium)
|
|
- Unobfuscated timestamps (Medium)
|
|
|
|
2. **Performance**:
|
|
- Web interface exceeds target (512ms vs 500ms)
|
|
- Data consistency between logs and benchmarks
|
|
|
|
## Recommendations
|
|
1. **Security Remediation**:
|
|
- Encrypt cron expressions using AES-256-GCM
|
|
- Obfuscate task IDs with HMAC
|
|
- Standardize timestamp formats
|
|
|
|
2. **Performance Improvements**:
|
|
- Implement response caching for web interface
|
|
- Review middleware processing chain
|
|
- Validate performance after security fixes
|
|
|
|
## Final Assessment
|
|
- Performance benchmarks meet architectural requirements (all under 800ms threshold)
|
|
- Security implementation meets core requirements but has outstanding medium severity issues
|
|
- Recommend conditional approval pending:
|
|
1. Security remediation completion
|
|
2. Final performance verification
|
|
|
|
## Next Steps
|
|
1. Create remediation tickets for outstanding issues
|
|
2. Schedule follow-up validation after fixes
|
|
3. Final approval before production deployment |