Goal-5: Security Implementation Status
Current Status
- Execution plan created (100%)
- Role inheritance system: Implemented (100%)
- Secrets management: Not started (0%)
- Vulnerability scanning: Not started (0%)
Task Progress
-
Task 5.1: Role inheritance implementation
- Status: Completed
- Assigned to: Security Specialist
- Completed: 5/3/2025
- Dependencies: Goal-1 (75%)
-
Task 5.2: Role Manager integration
- Status: Completed
- Assigned to: symphony-security-specialist, symphony-orchestrator
- Dependencies: Task 5.1 (Complete), Goal-4 (Complete)
- Completed: 5/3/2025
- Testing Assigned: symphony-checker
- Issues: Resolved
- Remediation Tasks:
- 5.2.1: Fix role inheritance implementation (parent_role → role_inheritance)
- Priority: Critical
- Due: 2025-05-04
- Completed: 5/3/2025
- Assigned: symphony-security-specialist
- 5.2.2: Implement signed OU claims validation
- Priority: High
- Due: 2025-05-04
- Completed: 5/3/2025
- Assigned: symphony-security-specialist
- 5.2.3: Complete audit log verification
- Priority: Medium
- Due: 2025-05-05
- Completed: 5/3/2025
- Assigned: symphony-security-specialist
- 5.2.1: Fix role inheritance implementation (parent_role → role_inheritance)
-
Task 5.3: Secrets storage design
- Status: Pending
- Assigned to: Security Specialist
- Dependencies: Goal-4 (100%)
-
Task 5.4: Secrets API implementation
- Status: Pending
- Assigned to: Security Specialist + Web Team
- Dependencies: Task 5.3
-
Task 5.5: Scanner core
- Status: Pending
- Assigned to: Security Specialist + MCP Team
- Dependencies: None
-
Task 5.6: Reporting system
- Status: Pending
- Assigned to: Security Specialist
- Dependencies: Task 5.5
Next Steps
- Begin Task 5.3 (Secrets storage design)
- Coordinate with Web Team for Task 5.4
- Review security validation report
- Update project status documentation