# Goal-6 Execution Plan: Proactive Engine
## Phase 1: Memory-Dependent Components (Can Start Now)
1. **Task-1**: Scheduled Task System Core
- Implement cron parser (depends only on Memory)
- Basic scheduler service
- Success Criteria: Can schedule/run simple memory operations
2. **Task-2**: NLP Integration Baseline
- LangChain memory adapter
- Intent classification service
- Success Criteria: Basic NLP commands work via CLI
## Phase 2: Interface-Dependent Components (Requires Goal-3)
1. **Task-3**: Web Scheduler Interface
2. **Task-4**: Event Bus Integration
## Dependencies
```mermaid
gantt
title Goal-6 Dependencies
dateFormat YYYY-MM-DD
section Blocked
Web Interface :active, 2025-05-10, 7d
section Ready
Memory System :done, 2025-05-01, 5d
section In Progress
CLI Base :active, 2025-05-05, 5d