Goal-4 Execution Plan: Memory System v1
Task Sequence
- Goal-4-Task-1: Design memory interface (prerequisite for all other tasks) [COMPLETE]
- Goal-4-Task-2: Implement core data structures (depends on Task-1) [COMPLETE]
- Goal-4-Task-3: SQLite integration (depends on Task-2) [COMPLETE]
- Goal-4-Task-4: Audit logging (depends on Task-1, can proceed in parallel) [COMPLETE]
Dependency Diagram
graph TD
A[Task-1: Interface Design] --> B[Task-2: Data Structures]
A --> C[Task-4: Audit Logging]
B --> D[Task-3: SQLite Integration]
Quality Gates
- Interface design must be reviewed by symphony-score
- Data structures must pass security review
- SQLite adapter must include encryption tests
- Audit logs must meet security baseline requirements
Risk Mitigation
- Early interface review to prevent rework
- Security validation at each stage
- Modular implementation to isolate dependencies