ai-agent/symphony-ai-agent/planning/Goal-4/Goal-4-execution-plan.md

941 B

Goal-4 Execution Plan: Memory System v1

Task Sequence

  1. Goal-4-Task-1: Design memory interface (prerequisite for all other tasks) [COMPLETE]
  2. Goal-4-Task-2: Implement core data structures (depends on Task-1) [COMPLETE]
  3. Goal-4-Task-3: SQLite integration (depends on Task-2) [COMPLETE]
  4. Goal-4-Task-4: Audit logging (depends on Task-1, can proceed in parallel) [COMPLETE]

Dependency Diagram

graph TD
    A[Task-1: Interface Design] --> B[Task-2: Data Structures]
    A --> C[Task-4: Audit Logging]
    B --> D[Task-3: SQLite Integration]

Quality Gates

  1. Interface design must be reviewed by symphony-score
  2. Data structures must pass security review
  3. SQLite adapter must include encryption tests
  4. Audit logs must meet security baseline requirements

Risk Mitigation

  • Early interface review to prevent rework
  • Security validation at each stage
  • Modular implementation to isolate dependencies