Goal-3 Execution Plan

graph TD
    A[Task-1: CLI Interface] --> B[Task-3: Integration Tests]
    C[Task-2: Web Interface] --> B
    B --> D[Task-4: Performance Benchmarks]

Implementation Sequence

  1. Parallel implementation:
    • Task-1: CLI interface foundation
    • Task-2: Web interface foundation
  2. Task-3: Integration testing
  3. Task-4: Performance validation

Quality Gates

  • Each interface requires security review
  • Cross-platform compatibility testing
  • <500ms response time for all interface operations

Success Criteria

  • Implements both CLI and Web interfaces
  • Supports all core orchestration commands
  • Maintains consistent interface versioning