# Goal-2 (RBAC Implementation) Execution Plan
## Task Sequence
1. Task-1: RBAC Core Implementation
2. Task-3: Negative Test Implementation (parallel with Task-1)
3. Task-2: TLS-RBAC Integration
4. Task-4: Audit Logging Integration
## Dependencies
```mermaid
graph TD
A[Goal-1 Completion] --> B[Task-1]
B --> C[Task-3]
B --> D[Task-2]
D --> E[Task-4]
```
## Quality Checkpoints
1. After Task-1: Security review of RBAC core
2. After Task-2: Integration test validation
3. After Task-4: Final security audit
## Iteration Plan
1. **Initial Implementation** (Tasks 1-3)
- Focus: Core functionality
- Duration: 5 days
- Exit Criteria: 90% unit test coverage
2. **Hardening Phase** (Tasks 3-4)
- Focus: Edge cases and audit logging
- Duration: 3 days
- Exit Criteria: 100% negative test coverage
3. **Final Validation**
- Focus: Security review
- Duration: 2 days
- Exit Criteria: Security team sign-off
## Risk Mitigation
- **Risk**: TLS-RBAC integration complexity
- **Mitigation**: Early prototype in Task-1
- **Risk**: Negative test coverage
- **Mitigation**: Dedicated Task-3 parallel track