# Goal-4 Execution Plan: Memory System v1
## Task Sequence
1. Goal-4-Task-1: Design memory interface (prerequisite for all other tasks) [COMPLETE]
2. Goal-4-Task-2: Implement core data structures (depends on Task-1) [COMPLETE]
3. Goal-4-Task-3: SQLite integration (depends on Task-2) [COMPLETE]
4. Goal-4-Task-4: Audit logging (depends on Task-1, can proceed in parallel) [COMPLETE]
## Dependency Diagram
```mermaid
graph TD
A[Task-1: Interface Design] --> B[Task-2: Data Structures]
A --> C[Task-4: Audit Logging]
B --> D[Task-3: SQLite Integration]
```
## Quality Gates
1. Interface design must be reviewed by symphony-score
2. Data structures must pass security review
3. SQLite adapter must include encryption tests
4. Audit logs must meet security baseline requirements
## Risk Mitigation
- Early interface review to prevent rework
- Security validation at each stage
- Modular implementation to isolate dependencies