# Goal-1-Task-4 Work Log - SecureAudit Implementation ## 2025-05-04 19:55:00 - Version Controller Review 1. Test report review complete: - Performance: 420ms response time (within 800ms threshold) - All functional tests passed 2. Security validation findings: - Callback encryption properly implemented (AES-256-GCM) - Medium severity issues identified: * Unencrypted cron expressions * Plaintext task IDs * Unobfuscated timestamps 3. Next steps: - Delegate security fixes to security team - Create release branch v0.1.1-security - Schedule production deployment after fixes verified ----Begin Update---- # Goal: Goal-1 # Task: Task-4 - Production Rollout Coordination Timestamp: 2025-05-04 20:27:00 Action: Updated release plan with security hold status Details: - Added HOLD status to v0.1.1 release - Documented blocking security issues - Updated deployment schedule to reflect delays ----End Update----